It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job?
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes 24 electricians 36 days to wire a new housing subdivision. How many days would 32 electricians take to do the same job? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.