A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?

+4
Answers (1)
  1. 6 October, 19:06
    0
    Step-by-step explanation:

    What is given:

    Formula to be used Z = (X - mean) / standard deviation

    Mean = 214

    X = 224

    Variance = 100

    Formula of Standard deviation = sqrt (variance) = sqrt (100) = 10

    So Z = (224 - 214) / 10 = 10/10 = 1

    For z = 1, the probability is 0.3413; 34.13% ⇒ The probability of project being completed by 224 days is 34.13%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers