30 Labour s take 20 days to complete a work. How many labour must be added to complete the same work in 15 days?

+2
Answers (1)
  1. 23 March, 12:56
    0
    30 labours ... 20 days

    x ... 15 days

    x = (30*20) / 15=2*20=40 labours.

    Labours added: 40-30=10

    Answer: 10 labours added.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “30 Labour s take 20 days to complete a work. How many labour must be added to complete the same work in 15 days? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.