a plumber laying 500 meters of drain pipe required 20 men of working for 10 days. What length in meters would be laid by 50 men in 5 days, if they all work at the same rate?

+1
Answers (1)
  1. 20 August, 09:54
    0
    500 meters = 20men = 10days

    To get the factor 500 / (20*10) = 5/2 meters/day

    For 50 men and 5days we don't know the meters

    So we go by 50 * (5/2) * 5 = 625meters
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “a plumber laying 500 meters of drain pipe required 20 men of working for 10 days. What length in meters would be laid by 50 men in 5 days, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.