Person A can complete a job in 6 hours. Person B can complete the same job in 4 hours. Working at the same rate, how many hours will it take both of them to complete the job?

+3
Answers (1)
  1. 1 May, 08:59
    0
    Answer: it will take both of them 2.4 hours to complete the job.

    Step-by-step explanation:

    Person A can complete a job in 6 hours. This means that the rate at which Person A can complete the job per hour is 1/6

    Person B can complete the same job in 4 hours. This means that the rate at which Person A can complete the job per hour is 1/4

    If they work together, they would work simultaneously and their individual rates are additive. This means that their combined working rate would be

    1/6 + 1/4 = 5/12

    Assuming it takes t hours for both of them to clean the room working together, the working rate per hour would be 1/t. Therefore,

    5/12 = 1/t

    t = 12/5

    t = 2.4 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Person A can complete a job in 6 hours. Person B can complete the same job in 4 hours. Working at the same rate, how many hours will it ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.