The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.