Ask Question
14 December, 02:20

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

+5
Answers (1)
  1. 14 December, 03:22
    0
    Answer: the due date would be 92 weeks

    Step-by-step explanation:

    Since the time required to complete a project is normally distributed, we would apply the formula for normal distribution which is expressed as

    z = (x - µ) / σ

    Where

    x = number of weeks.

    µ = mean

    σ = standard deviation

    From the information given,

    µ = 80 weeks

    σ = 10 weeks

    If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, the z score corresponding to 90% (90/100 = 0.9) is 1.29

    Therefore,

    1.29 = (x - 80) / 10

    x - 80 = 1.2 * 10

    x - 80 = 12

    x = 80 + 12 = 92
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers