A cased and cemented hole with a measured depth of 7112 ft is perforated from 6967 ft to 6992 ft. the customer wants tubing to be at least 90 ft above the top of the perforations but wants the tubing to be at the rig floor located 18 ft above ground level. John is using 33 foot joints of tubing. how many joints should he use to satisfy the customers request?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A cased and cemented hole with a measured depth of 7112 ft is perforated from 6967 ft to 6992 ft. the customer wants tubing to be at least ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.