A man can clear his driveway using a snowblower in 45 minutes. It takes his son 2 hours to clear the driveway using a shovel. About how long would it take them to clear the driveway if they worked together?

+5
Answers (1)
  1. 22 January, 02:33
    0
    Father's rate: 1/45 (driveways/minute)

    Son's rate: 1/120 (driveways/minute: 2 hours equals 120 minutes)

    combined rate: 1/45 + 1/120 = 11/360 (driveways/minute)

    time at combined rate: 1 / (11/360) =

    360/11 minutes =

    32.73 minutes, which is about 33 minutes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A man can clear his driveway using a snowblower in 45 minutes. It takes his son 2 hours to clear the driveway using a shovel. About how ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.