If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21days?

+5
Answers (1)
  1. 3 June, 01:07
    0
    Total work amount

    6 men * 14 days

    84 men days

    If it is done within 21 days, need x men

    84 men days = x men * 21 days

    x = 84/21 men

    x = 4 men
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21days? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.