a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time, how many hours will it take to complete the project

+2
Answers (1)
  1. 8 January, 03:36
    0
    It will take about 240 hours to complete the project, I am very sorry if my answer is incorrect
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.