A person-hour is a unit of measure representing one person working for one hour. A construction foreman estimates that it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time how many hours will it take to complete the project?

+5
Answers (1)
  1. 4 February, 00:03
    0
    We need 2880 person-hours and we have 12 people.

    When we divide the work between them: 2880/12 = 240 hours required to complete.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A person-hour is a unit of measure representing one person working for one hour. A construction foreman estimates that it will take 2880 ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.