12 men working 8 hours a day complete a piece of work in 10 days to complete a the same work in 8 days working 15 hours a days the number of men required is

+2
Answers (1)
  1. 22 November, 11:05
    0
    12 men : 8 hours : 10 days

    / / Find if every man works 1 hour

    12 x 8 men : 1 hour : 10 days

    96 men : 1 hour : 10 days

    //Find if every man works 15 hours

    96 : 15 men : 15 hours : 10 days

    6.4 men : 15 hours : 10 days

    //Find if every man works 1 day

    6.4 x 10 men : 15 hours : 1 day

    64 men : 15 hours : 1 day

    //Find if every man works 8 days

    64 : 8 men : 15 hours : 8 days

    8 men : 15 hours : 8 days

    Answer: 8 men is needed
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “12 men working 8 hours a day complete a piece of work in 10 days to complete a the same work in 8 days working 15 hours a days the number ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.