ll the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. a How many hours would this job take if the number of workers decreased by factor of 2?

+2
Answers (1)
  1. 10 July, 23:32
    0
    44 hours

    Step-by-step explanation:

    Decreasing the people by a factor of 2 means we have 3 people

    The job takes 6 * 22 = 132 people hours

    When we decrease the people, it will take more hours

    132 people hours = 3 people * t hours

    Divide each side by 3

    132/3 = 3t/3

    44 = t

    It will take 44 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “ll the members of a construction crew work at the same pace. Six of them working together are able to pour foundation in 22 hours. a How ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.