It takes 10 days for 12 men to paint 4 walls. At this rate, how long will it take 6 men to paint 3 walls?

Answer

+5
Answers (1)
  1. 29 July, 16:30
    0
    Answer: 15 days

    Step by step explanation:

    It would take 20 days for 6 men to paint 4 walls because

    half the people would mean double the time and 10 * 2 = 20

    Because the 6 men are only painting 3 walls we would

    get rid of a quarter of the time that it would take and 20 * 0.75 = 15
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes 10 days for 12 men to paint 4 walls. At this rate, how long will it take 6 men to paint 3 walls? Answer ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.