All members of a construction crew work at the same pace. Four of them working together can pour a foundation in 32 hours. How many hours would the job take if the number of workers:

decreased 2 times

+5
Answers (1)
  1. 28 August, 00:37
    0
    It would take them 64 hours. However, this is only true if they decrease by two in the end. The question is not very specific.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “All members of a construction crew work at the same pace. Four of them working together can pour a foundation in 32 hours. How many hours ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.