A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates. What is the probability that the project will finish on or before 50 days?

+2
Answers (1)
  1. 14 June, 15:14
    0
    As critical path is the longest path during estimation, so 50 days is maximum time to complete this project. So probability to complete a project before 0n 50 days or before 50 days days is 1

    Pr=1
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.