Ask Question
12 April, 03:09

A construction company has to complete a project no later than 4 months from now or there will be significant cost overruns. The manager of the construction company believes that there are four possible values for the random variable X, the number of months from now it will take to complete this project: 2, 2.5, 3, and 3.5. It is currently believed that the probabilities of these four possibilities are. 4,.3,.2, and. 1, respectively. What is the expected completion time (in months) of this project from now?

+4
Answers (1)
  1. 12 April, 05:13
    0
    The expected completion time of this project from now is 2.5 months.

    Step-by-step explanation:

    To find the expected completion time for the project, we multiply each projection by it's probability.

    We have that:

    0.4 = 40% probability it takes 2 months to complete the project.

    0.3 = 30% probability that it takes 2.5 months to complete the project.

    0.2 = 20% probability it takes 3 months to complete the project.

    0.1 = 10% probability it takes 3.5 months to complete the project.

    What is the expected completion time (in months) of this project from now?

    E = 0.4*2 + 0.3*2.5 + 0.2*3 + 0.1*3.5 = 2.5

    The expected completion time of this project from now is 2.5 months.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A construction company has to complete a project no later than 4 months from now or there will be significant cost overruns. The manager of ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers