A tomato grower needs to ship early when prices are high and spoilage is low. She now has 25 tons on hand and by can add two tons a week by waiting. The current profit is $250 per ton but it will reduce $15 per ton for each week she delays. When should she ship to receive the maximum profit?

+1
Answers (1)
  1. 11 July, 05:01
    0
    On first week

    Quantity of tomato = 25 tons

    profit per ton = $250

    So if she sells tomato on first week then total profit = 25 * 250 = $6250

    On second week

    Quantity of tomato = 27 ton

    profit per kg = $ 235

    So if she sells tomato on second week then total profit = 27 * 235 = $6345

    On third week

    Quantity of tomato = 29 ton

    Profit per kg = $220

    So if she sells tomato on third week then total profit = 29*220 = $6380

    Now consider fourth week

    Quantity of tomato = 31 ton

    Price per kg = $205

    So if she sells tomato on fourth week then total profit = 31*205 = $6355

    so she must ship her tomatoes on third week i. e she will attain $ 6380 as profit.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A tomato grower needs to ship early when prices are high and spoilage is low. She now has 25 tons on hand and by can add two tons a week by ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.