A ramp is being constructed with wood and then filled with concrete. How many cubic get of concrete will be needed to complete the ramp?

+2
Answers (1)
  1. 16 May, 03:23
    0
    The cubic volume of concrete needed to complete the ramp is 360 ft³

    Step-by-step explanation:

    We note that the ramp shape is that of a right ngled triangular cube with dimensions

    Height = 10 ft

    Base = 12 ft

    Width = 6 ft

    The amount of concrete to fill the ramp is approximately the volume of the ramp.

    Volume of ramp = volume of triangular prism = 0.5*Base * Height * Width

    Volume of ramp = 0.5*12*10*6 = 360 ft³.

    The cubic volume of concrete needed to complete the ramp = 360 ft³.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A ramp is being constructed with wood and then filled with concrete. How many cubic get of concrete will be needed to complete the ramp? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.