We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 2 weeks 25% of the time, 4 weeks 50% of the time and 6 weeks 25% of the time. How long does the project now take to complete (on average)

+4
Answers (1)
  1. 10 November, 01:38
    0
    On average, the project takes 4 weeks to complete.

    Step-by-step explanation:

    We have these following probabilities:

    25% probability that the activity takes 2 weeks.

    50% probability that the activity takes 4 weeks.

    25% probability that the activity takes 6 weeks.

    How long does the project now take to complete (on average)

    We multiply each duration by it's probability.

    0.25*2 + 0.5*4 + 0.25*6 = 4

    On average, the project takes 4 weeks to complete.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.