We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 2 weeks 25% of the time, 4 weeks 50% of the time and 6 weeks 25% of the time. How long does the project now take to complete (on average)
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “We ask the engineers working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.