Your heavy-duty mechanics earn $30.00 per hour. Your light-duty servicemen earn $10.50 per hour. Assume a customer wants his engine tuned, oiled, and greased. If the job takes 1 1/2 hours of a mechanic's time, 1 1/2 hours of a serviceman's time, and the overhead rate is 100%, what are the total labor plus overhead charges?

+3
Answers (2)
  1. 23 October, 23:10
    0
    The answer to that is 121.50
  2. 24 October, 00:40
    0
    Total charge

    [ (30*1.5) + (10.5*1.5) ]+100%=60.75

    100%=60.27

    So total charge is

    (30*1.5) + (10.5*1.5) + 100%=121.50
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Your heavy-duty mechanics earn $30.00 per hour. Your light-duty servicemen earn $10.50 per hour. Assume a customer wants his engine tuned, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.