You have just timed a person doing a job a few times. the first time it took the person 25 minutes, the second time it took 20 minutes, and the third time it took 17.55 minutes. which learning curve unit improvement factor should you use?

+3
Answers (1)
  1. 15 May, 12:40
    0
    solution:

    T1 = time required for first unit = 25 minutes

    T2 = time required for 2nd unit = 20 minutes

    T3 = time required for 3rd unit = 17.55 minutes

    Tn = time required for nth unit

    Learning rate from 1st to 2nd unit = Time required for 2nd unit/time required for 1st unit = L2 / L1

    T2 / T1 = 20/25 = 0.80
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You have just timed a person doing a job a few times. the first time it took the person 25 minutes, the second time it took 20 minutes, and ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.