Ask Question
22 June, 18:58

four men working together can create a trench in 42 days. they begin the job but one man works only half days. How long will it take to complete the trench?

+4
Answers (1)
  1. 22 June, 20:32
    0
    48 days

    Step-by-step explanation:

    Four men working together can create a trench in 42 days.

    Find the number of man-days to complete the job

    4*42 = 168 man-days

    They begin, but one man works only half-days.

    How long will it take to complete the job?

    Let d = no. days to complete the trench

    d (3 + 0.5) = 168

    d (3.5) = 168

    3.5d = 168

    d = 168/3.5

    d = 48 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “four men working together can create a trench in 42 days. they begin the job but one man works only half days. How long will it take to ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.