Six workers can do 9 identical jobs in 3 days. How long will it take 4 workers to do 10 such jobs?

A) 3 days

B) 4 days

C) 5 days

D) 6 days

E) more than 6 days

I guess it's ans is D.

+2
Answers (1)
  1. 5 July, 13:17
    0
    6 workers-9 jobs in 3 days

    In one day 6 workers can do 3 jobs

    In one day 1 worker can do 0.5 job

    4 workers can so 2 jobs in a day

    So. They can do 10 jobs in 5 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Six workers can do 9 identical jobs in 3 days. How long will it take 4 workers to do 10 such jobs? A) 3 days B) 4 days C) 5 days D) 6 days ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.