If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are 1,600 units at $13, the direct materials quantity variance is $5,200 favorable.

+2
Answers (1)
  1. 24 May, 02:05
    0
    The answer is FALSE

    Step-by-step explanation:

    Materials quantity variance = (SQ - AQ) * SP

    = (2,000 - 1,600) * 12

    $4800 Favourable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.