How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?

+4
Answers (1)
  1. 25 January, 06:44
    0
    8 workers can complete a task in 10 days, meaning the man-hours needed to this task is 80 man-hours.

    Hence for 5 workers to complete the same task that require 80 man-hours, 80:5 = 16.

    So, it will take 16 days for 5 workers to complete this task.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.