Ashanti Goldfields, wanted to undertake a project which will costs GH 30,000 now and is expected to generate year - end cash inflows of GH 9000, GH 8000, GH 7000, GH 6000, GH5000 and GH 4000 in years 1 through 6. The opportunity cost of capital may be assumed to be 10 percent.

+5
Answers (1)
  1. 12 June, 00:03
    0
    I strongly believe that NPV of the project is the requirement of this question:

    NPV is - $486.82

    Step-by-step explanation:

    The NPV is the present value of the future cash flows from year 1 through year 6 minus the initial capital investment of GH30,000

    The cash flow discount factor = 1 / (1+r) ^n

    r is the opportunity cost of capital at 10%

    n is the relevant year of each cash flow

    NPV=-30,000+9000 / (1+10%) ^1+8000 / (1+10%) ^2+7000 / (1+10%) ^3+6000 / (1+10%) ^4+5000 / (1+10%) ^5+4000 / (1+10%) ^6=-$486.82

    The project is not viable since NPV is negative
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Ashanti Goldfields, wanted to undertake a project which will costs GH 30,000 now and is expected to generate year - end cash inflows of GH ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.