Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total cost of $61610. Bonita's labor quantity variance is

+4
Answers (1)
  1. 28 December, 12:40
    0
    1800

    Step-by-step explanation:

    Labor quantity variance = Actual quantity * standard price - standard quantity * standard price

    Standard quantity=2*2600=5200

    Labor quantity variance

    5050*12-5200*12=1800
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.