Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machine Y. At these rates, if the two machines together produce 54 w widgets in 3 days, how many days would it take machine X alone to produce 2w widgets? A4 B6 C8 D10 E12

+1
Answers (1)
  1. 18 April, 03:29
    0
    Step-by-step explanation:

    Work done = rate * time

    let time taken by X to produce w widgets be t days

    rate = w/t

    Since X take 2 days longer rate for Y would be

    rate = w/t-2

    combined rate is (w/t+w/t-2)

    Since in 3 days both x and y can produce 5w/4

    (w/t+w/t-2) = 5w/4

    5t2 - 34t + 24=0

    (t-6) (t-4/5) = 0

    t=6 or t=4/5 (not possible because t-2 (time taken by Y) comes out to be - 6/5 which is not possible)

    so t=6 days which is the time taken by X to produce w widgets

    so time taken to produce 2w widgets will be 12 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machine Y. At these rates, if the two ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.