Ask Question
5 April, 01:29

a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

+2
Answers (2)
  1. 5 April, 01:47
    0
    1 house = 6 men x 5 days = 30 man days

    Need 30 man days with only 5 men: 30x = 5 men → x = 6

    It will take 6 days for 5 men to complete the job.

    Answer: 6 days
  2. 5 April, 02:48
    0
    It will take 4 days to paint the house with 5 men
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.