State what kind of variation you have, then solve the problem. A 15-person road crew is scheduled to finish repairing a highway in 8 days. On the morning of the fifth day, several new workers join the crew and together they complete the remaining repairs in 2 days. How many new workers were there?

+1
Answers (1)
  1. 4 May, 09:20
    0
    ==> 6 (15+x) = 120

    ==> 15+x = 20

    ==> x = 5.

    Therefore five new workers joined the crew.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “State what kind of variation you have, then solve the problem. A 15-person road crew is scheduled to finish repairing a highway in 8 days. ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.