On a new construction site an electrician can install a new light fixture in 20 minutes a project cost for 24 new fixtures to be installed on each of four floors if a work day is 8 hours how many work days will it take to electricians to complete the installation

+2
Answers (1)
  1. 6 July, 16:53
    0
    1 new light fixture = 20 minutes24 new fixtures = 24 x 20 = 480 min

    we know, 480 min = 60min x 8 hour (a day of work)

    total = 4 floors1 floor > 24 fixtures = 1 day2 floor > 24 fixtures = 1 day3 floor > 24 fixtures = 1 day4 floor > 24 fixtures = 1 day >> total 4 days (8hrs each day)

    from question, we found that: For 24 fixture - he needs 480 min (or 8hr) which is nothing but 1 work day. now, 1 floor > 24 fixtures = 1 day 2nd floor > 24 fixtures = 2nd day

    ... And on 4th Day he finishes, a) Floor >1 floor + 2 floor + 3 floor + 4 floor b) Fixture> 24+24+24+24 = 96 fixturesc) Days> 4 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “On a new construction site an electrician can install a new light fixture in 20 minutes a project cost for 24 new fixtures to be installed ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.