Task

Precedence

Time (min)

Best Vision is revamping its assembly lines to improve efficiency. As shown below, there are 10 steps to assembling a television set.

If Best needs to produce 120 televisions in a 40-hour work week, how should the line be balanced? Given that one worker is assigned to each workstation, how many workers are required to operate the line? What is the efficiency of the line?

If demand for televisions is reduced to 100 sets per 40-hour week, how many workers will be needed to man the line? Re-balance the line and re-calculate its efficiency.

Task

Precedence

Time (min)

A

None

8

B

A

4

C

A

7

D

A

3

E

B

7

F

C, E

11

G

D

2

H

G

8

I

F, H

5

J

I

7

+2
Answers (1)
  1. 25 October, 22:04
    0
    Henry part 3 my family and
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Task Precedence Time (min) Best Vision is revamping its assembly lines to improve efficiency. As shown below, there are 10 steps to ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers