It takes 4000 persons hours to complete a project. How many weeks will it take a team of 5 people to complete the project if each person works 8 hours a day, 5 days a week?

+4
Answers (1)
  1. 11 February, 10:56
    0
    4000/5 people = 800 hours per person.

    5x8 = 40 hours a week per person

    40x5 people = 200 hours a week with all 5 people working.

    800/200 = 4 weeks

    The answer is 4 weeks
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It takes 4000 persons hours to complete a project. How many weeks will it take a team of 5 people to complete the project if each person ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.