Crew a can tunnel through a mountain in 30 days. if crew B starts from the other side at the same time, the tunnel can be completed in 18 days. how long would it take crew B working alone?

+2
Answers (1)
  1. 5 October, 21:33
    0
    39 days because 1/2 of 18 = 9 and 9 plus 30 = 39
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Crew a can tunnel through a mountain in 30 days. if crew B starts from the other side at the same time, the tunnel can be completed in 18 ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.