A crane can lift a 900 kg mass to height of 50 m in 2 minutes. Calculate the work

done by the crane.

+2
Answers (1)
  1. 23 August, 09:51
    0
    The work done by the crane is, W = 441000 J

    The power of the crane is, p = 3675 watts

    Explanation:

    Given data,

    The mass of the object, m = 900 kg

    The object is lifted to the height, h = 50 m

    The time taken to lift the mass, t = 2 min

    = 120 s

    The work done by the crane on the object is equal to the potential energy of the object at that height. It is given by the formula,

    W = P. E = mgh joules

    Substituting the values in the above equation

    W = 900 kg x 9.8 m/s² x 50 m

    = 441000 J

    The work done by the crane is, W = 441000 J

    The power of the crane,

    P = W / t

    = 441000 J / 120 s

    = 3675 watts

    Hence, the power of the crane is, p = 3675 watts
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A crane can lift a 900 kg mass to height of 50 m in 2 minutes. Calculate the work done by the crane. ...” in 📘 Physics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.