In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

a) true

b) false

+1
Answers (1)
  1. 1 November, 08:29
    0
    The correct answer is True.

    Explanation:

    This type of practice is common to evaluate the conditions in the most pessimistic scenario. The 99% accuracy is fundamental to set the most pessimistic duration of a project, because it guarantees to have a high confidence interval to ensure that the actual duration will be equal or less than the most pessimistic duration.

    Have a nice day!
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% ...” in 📘 Physics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers