A cable applies a vertical force to a crate with a mass of 70.0 kg. It first lifts the crate to a height of 12.0 m above the floor, and then lowers it back to the floor. What is the total work done by the force?

+1
Answers (1)
  1. Today, 01:30
    0
    The total work done is zero.

    Explanation:

    Given;

    mass of the crate, m = 70.0 kg

    height above ground through which the crate is lifted, h = 12.0 m

    The only work associated in lifting and lowering this crate is gravitational potential energy.

    Potential Energy during lifting = - mgh

    = - 70 x 9.8 x 12

    = - 8232 J

    Potential Energy during lowering = mgh

    = 70 x 9.8 x 12

    = 8232 J

    Total total work done by the force = - 8232 J + 8232 J = 0

    Therefore, the total work done is zero.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A cable applies a vertical force to a crate with a mass of 70.0 kg. It first lifts the crate to a height of 12.0 m above the floor, and ...” in 📘 Physics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.