Ask Question
5 July, 18:34

How much work must be done on a 5-kg sled to increase its speed from 10

m/s to 15 m/s?

A. 25

B. 312.5 J

C. 562.5 J

D. 5

+1
Answers (1)
  1. 5 July, 21:34
    0
    B. 312.5 J

    Explanation:

    Work = change in energy

    W = ½ mv₂² - ½ mv₁²

    W = ½ m (v₂² - v₁²)

    W = ½ (5 kg) ((15 m/s) ² - (10 m/s) ²)

    W = 312.5 J
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “How much work must be done on a 5-kg sled to increase its speed from 10 m/s to 15 m/s? A. 25 B. 312.5 J C. 562.5 J D. 5 ...” in 📘 Physics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers