A crane does 9,500 j of work to lift a crate straight up using a force of 125 n. how high does the crane lift the crate?

+2
Answers (1)
  1. 7 August, 13:34
    0
    Work is calculated by multiplying the amount of force exerted by the distance that the object was displaced. The equation is,

    Work = Force x displacement

    Therefore, displacement is the quotient when work is divided by force.

    displacement = 9500 J / 125 N

    = 76 m

    Therefore, the crane was lifted 76 meters above the ground.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A crane does 9,500 j of work to lift a crate straight up using a force of 125 n. how high does the crane lift the crate? ...” in 📘 Physics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.