In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

+5
Answers (1)
  1. 10 May, 20:29
    0
    Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as: ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.