You are involved in an Information Systems project. The project's scope has widened, but there is no change in cost, quality, and user expectations. This will result in an increase in time taken to complete the project.

+3
Answers (1)
  1. 26 October, 01:11
    0
    Answer: Yes

    Explanation: This will increase the time frame of the project because the scope has widened (I. e more deliverables) it will require more time to achieve what has changed since it was not in the plan initially and initial plan has a timeframe, so as the scope widens, timeframe increases.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You are involved in an Information Systems project. The project's scope has widened, but there is no change in cost, quality, and user ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.