The "Control" phase of the Six Sigma DMAIC is intended to ensure that:

a. the proper subset of process inputs are monitored.

b. variability reduction is pursued.

c. data analysis is overseen.

d. inputs are closely monitored.

e. improvements are sustained.

+2
Answers (1)
  1. 30 January, 02:23
    0
    e. improvements are sustained.

    Explanation:

    Ensuring that the gains obtained during a project are maintained long after the project has ended is the primary objective of the DMAIC Control phase.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The "Control" phase of the Six Sigma DMAIC is intended to ensure that: a. the proper subset of process inputs are monitored. b. variability ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.