In a critical path analysis, the shortest path is what drives the completion date for the project. True False

+4
Answers (1)
  1. 18 June, 17:48
    0
    False.

    Explanation:

    Critical Path Analysis or CPA can be defined as a technique used in project management. This project management technique was developed by James Kelly and Morgan Walker in the 1950s. In this technique, analysis, planning, and scheduling of large projects are done.

    The Critical Path Analysis is the longest path in the project management as it set steps from start to finish.

    So, the given statement is false, as CPA is not the shortest but the longest path that sets the completion date.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In a critical path analysis, the shortest path is what drives the completion date for the project. True False ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers