A distribution system comprises 2 central distribution centers (which are both replenished from a single plant), 8 regional warehouses, and 56 stores. The replenishment lead times are as follows: plant (2 weeks), DC (1 week), regional warehouse (1 week), store (1 week). What is the minimum planning horizon?

+4
Answers (1)
  1. 23 April, 04:57
    0
    5 weeks.

    Explanation:

    The replenishment lead times are 2 weeks for the plant, 1 week for the DC,! week for the regional warehouse and 1 week for the store.

    The planning horizon is the amount of time that will be required by an organization when the organization is preparing for a strategic plan.

    So the minimum planning horizon is 5 weeks.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A distribution system comprises 2 central distribution centers (which are both replenished from a single plant), 8 regional warehouses, and ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers