You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called Design-Build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction at the same time the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of which of the following?

a. Progressive elaboration

b. An iterative phase relationship

c. Handoffs Managing

d. the projects as a program

+5
Answers (1)
  1. 5 May, 02:46
    0
    (D) The project as a program

    Explanation:

    A project represents a single, focused endeavour. A program is a collection of projects.

    Having a construction team to work on the first mile of the highway, and having the design team for their construction as well. So this makes it a program.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers