Scope Change Control is primarily concerned with: a. Influencing the factors that create scope changes. b. Defining a baseline for performance measurement and control. c. Developing a written scope statement which will serve as the basis for future project decisions. d. Assigning work elements to the proper organizations.

+2
Answers (1)
  1. 26 November, 10:41
    0
    A - Influencing the factors that create scope changes.

    Explanation:

    Scope Change Control is process of project management that ensure the possible changes that may occur during the process of the project execution is well managed in such a way that such changes do not affect the outcome or success of the project. There is no doubt that scope change is inevitable in project, and so many factors could lead to change in the course of project execution, so this concept entails change management during project execution.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Scope Change Control is primarily concerned with: a. Influencing the factors that create scope changes. b. Defining a baseline for ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers