Incident managers begin planning for the demobilization process:

a. when incident activities shift from response to recovery.

b. right before the first resources are ready to be released.

c. as soon as possible to facilitate accountability of the resources.

d. after being requested by the emergency operations center

+5
Answers (1)
  1. 8 March, 06:59
    0
    The answer is C, as soon as possible to facilitate accountability of the resources.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Incident managers begin planning for the demobilization process: a. when incident activities shift from response to recovery. b. right ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.