Incident managers begin planning for the demobilization process when:

a. Incident activities shift from response to recovery.

b. The first resources are ready to be released.

c. Requested by the emergency operations center.

d. They begin the resource mobilization process.

+2
Answers (1)
  1. 8 January, 02:48
    0
    Incident managers begin planning for the demobilization process when the first resources are ready to be released. They also produce the management information such as KPIs and reports. They monitor the effectiveness of the incident management and create recommendations.

    The answer would be letter B.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Incident managers begin planning for the demobilization process when: a. Incident activities shift from response to recovery. b. The first ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers