A favorable cost variance occurs when actual costs are more than standard costs standard costs are more than actual costs standard costs are less than actual costs actual costs are the same as standard costs

+2
Answers (1)
  1. 27 October, 04:50
    0
    A favorable cost variance occurs when: Standard costs are more than actual costs

    Standard cost refers to the cost that projected to happen when acquiring an asset. Meanwhile, actual cost refers to the total cost that actually happens when acquiring that asset.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A favorable cost variance occurs when actual costs are more than standard costs standard costs are more than actual costs standard costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.